Audit of water infrastructure modernisation project found UAH 305.4 million of unfinished works

The Accounting Chamber approved on 24 November the audit report on the “Urban Infrastructure Development Project - 2”, which identified incomplete works totalling UAH 305.4 million.

The audit covered 2023-2025 with separate data for 2026; the deputy Chair Serhii Kliuchko was listed as responsible for the control measure.

Incomplete works on specific facilities

The audit found cases of incomplete works amounting to UAH 305.4 million. The causes cited included contract terminations, contractors’ failure to fulfil obligations and unfinished installation works.

unfinished sewage treatment plant with equipment

Among the incomplete works identified is the unfinished reconstruction of the sewage treatment facilities in Ternopil due to the contractor’s failure to meet contractual obligations, along with other examples of work stoppages.

Assets not commissioned and unused equipment

The audit recorded assets with a total value of almost UAH 1.6 billion that were used without being commissioned. It also found equipment procured with loan funds worth UAH 46.7 million that was not used for its intended purpose.

The unused equipment was located in Kharkiv due to unfinished installation, and in Zhytomyr in warehouses. Key causes of the shortcomings included delays in signing contracts and executing payments.

The project, financing and deadlines

The project began in 2014 with support from the International Bank for Reconstruction and Development (IBRD) and the Clean Technology Fund to modernise water supply, improve the energy efficiency of sector enterprises and enhance service quality.

The project closing date was set as 30 June 2025. The total funding envelope was USD 224.7 million, with USD 7.2 million of loan funds remaining unallocated for project activities.

Examples of unrealistic scheduling and execution delays

The audit uncovered unrealistic scheduling: the municipal enterprise (KP) «Kharkivvodokanal» signed contracts for the reconstruction of sewage treatment facilities with a completion period of 18 calendar days, whereas the design documentation envisaged between five months and one year.

At the municipal enterprise (KP) «Brovaryteplovodoenerhiia» late payments led the contractor to halt work for a total of 14 months. The audit text also points to the overall ageing of the infrastructure: about a third of water mains have exceeded their normative service life, and the wear of wastewater system equipment stood at 63.5%.