Kyiv prepares for winter - 80% of homes to be provided with backup heat

In Kyiv, six backup heat-supply facilities are being constructed in the zone of the Darnytsia CHP (combined heat and power plant); by the end of the year they plan to create the technical capability to provide backup heat to 80% of homes, the State Agency for Restoration and Development of Infrastructure of Ukraine reported.

Digital control of facilities

The Agency divides its efforts according to the principle 80% on urgent problems and 20% on strategic tasks. During the first 2.5 months it conducted an audit of regional services, which revealed differences in operational efficiency, unrealistic construction schedules and the absence of a unified system for operational control.

It has established digital monitoring of the facilities, which makes it possible to see actual readiness, financing, work progress and problem areas. “Now each facility is under digital control. We see actual readiness, financing, work rates and problem issues. This allows us not to wait for deadline failures but to respond to risks in advance,” the State Agency for Restoration and Development of Infrastructure of Ukraine said.

construction of heating networks near the CHP, workers

Protection of Kyiv region’s energy infrastructure

One task is to complete the construction of protective structures at substations in Kyiv region. According to the Agency, the ministry’s decision on the transfer is already in place, but they are awaiting the relevant acts from the Kyiv Regional Military Administration (RMA) before starting audits and selecting contractors.

Depending on the readiness of the facilities, the work may take from three weeks to four months. “We are ready to complete the unfinished protective structures at substations. The ministry’s decision on the transfer is already in place; we are awaiting the relevant acts from the Kyiv Regional Military Administration (RMA). Next - an audit, selection of contractors and completion of construction,” the Agency said.

Preparation for the heating season and road works

The Agency stresses the need to begin preparing for the next heating season now, because the full cycle of building protective structures takes six to eight months. Decisions that affect the readiness of infrastructure for winter need to be made in good time.

At the same time, work is under way on maintaining road infrastructure, winter road maintenance, and preparing repairs and bridge construction. The Agency emphasises the clear definition of tasks, deadlines and responsibilities of managers and daily monitoring of plan implementation to speed up the protection of critical infrastructure.